Answered: NEC3 ECS: Under Option A Contract can the client levy both Contra Charges and Liquidated Damages?

$
0
0
Usually liquidated damages are an exhaustive remedy for failure to complete the works by the Completion Date and the Subcontractor does have the right to under the Sub-subcontract to deduct these from amounts due. However, Z54 appears to also give the Subcontractor the right to recover other amounts from you.