Answered: NEC ECC: Should QS and PM Time be applied to Compensation events in NEC4 Option C Contract?

$
0
0
Correct - the contract intends that only additional cost for any QS and PM time would be recoverable. If they are full time on the job anyway, and were able to price this whilst doing the day job then there is no additional cost. If the Contractor can prove they had to bring in an additional resource just to work on the quote then this would be recoverable.

There could be arguments either way what is right or fare with this aspect, but this is the stance that the NEC has taken and on balance I think it is the most fair solution as any other answer would tip the balance too much towards one party or the other.