We are being employed on a labour only basis to carry out 4 phases of work. Under X18 we asked that the Contractors Liability to the Client for indirect or consequential loss to be capped at 10% of the contract value for each phase. The 1st Phase is worth £400k for example, but the client want this to be £10 million (The overall contract sum is £2million over 2 years) - Surely this is a unreasonable figure?
In addition to this they are also proposing a delay damages daily charge under X7