We are currently operating on a main option A with X1 in the options, the contractor has been applying for inflation within the completed activities but has not been applying inflation to agreed CE's, We are now at a point when some completed activities that have been adjusted by a CE are due and they are applying inflation to the revised amount not the original.
↧