Answered: NEC ECC: Challenge of a Z Clause relating to Corona Virus

$
0
0
Not directly it seems.

Up until yesterday though, the requirements to close non-retail 'premises' was not a legal requirement. It is now due the Coronavirus Bill being enacted and becoming law i.e. an Act.

If the Pm has given instructions though, as per clause 19.1, which change the Works Information (NEC3)/ Scope (NEC4) then this could be a compensation event under 60.1(1).