It does sound like it doesn't it, but it would be so much easier if the Project Manager uses the correct clause reference when they ask for a quotation. When they ask for a quote under clause 61.1 you are to proceed with the works. When they ask for a quote under 61.2 it is a proposed quote that you do NOT proceed with in the meantime.
For the avoidance of doubt I was ask them to confirm. It is important to establish this switch point as you need to know if you should be proceeding with the works.
For the avoidance of doubt I was ask them to confirm. It is important to establish this switch point as you need to know if you should be proceeding with the works.