Modified Contract based on NEC3 Option B.
Clause 19 has been deleted by Option Z. Clause 60.1(19) has not been deleted.
Construction is continuing though the Contractor is finding that many of its suppliers have shut down or are operating at reduced capacity as a result of their responses to the COVID-19 pandemic.
Contractor has issued an EWN advising that it has had to change suppliers, and that costs of materials have increased as a consequence.
Would this be a CE? If so, under which clause?
Clause 19 has been deleted by Option Z. Clause 60.1(19) has not been deleted.
Construction is continuing though the Contractor is finding that many of its suppliers have shut down or are operating at reduced capacity as a result of their responses to the COVID-19 pandemic.
Contractor has issued an EWN advising that it has had to change suppliers, and that costs of materials have increased as a consequence.
Would this be a CE? If so, under which clause?