NEC3 - Option B. Works have been suspended under cl34.1. Quotation requested.
We are preparing quotation for suspension, we cannot re-allocate the labour and staff, we have off-hired all plant.
Is it reasonable to include all suspended labour and staff in CE quotation (for the full duration of suspension) or can the PM instruct us to furlough the workforce to mitigate his costs?