NEC ECC: Can a CE be issued to omit works from Works Information if a CE was issued in error for this item of work?

$
0
0
We have an NEC3 project Option A. There has been change in personnel.

Current personnel have identified that an CE has been issued for Contractor Design element which is clearly required and noted in the Works Information as required.

The Contractor wants paid for the Works Information and has been paid the CE.

Can a CE be issued now to deduct the works in the Works Information as the CE issued deals with this - otherwise the Contractor is claiming the Works Information work payment and the CE (Works Information works were identified in part in the Activity Schedule).

Thank you