X5 &7- Contractor cost incurred

$
0
0
Thanks Glenn, just to clarify - Contractor contract has sectional compl. dates with Employer.  I want to know can I claim back these damages/costs from subcontractor, and yes this subcontractors risk.  subcontractors contract has 25.3 and x7.  

25.3 - two bullet points states and this is also the SC view that I can claim any additional money for carrying out work or having to pay the employer or others in carrying out work only.  therefore I can't claim back the damages incurred from them under 25.3.  

And if I can claim for additional cost incur as per 25.3 can I also claim for delay damages x7 as both these are the contract.

Note: NEC - A Commentary - key date - seems to imply that once you claimed under 25.3 you cant claim under any other damages clauses.   " 25.3 replaces rather than stand alternative to any damages clause."

I appreciate your feedback.