Answered: NEC ECC: Impact of CE following Contractor Delay on the Completion Date

$
0
0
Taken in isolation, by the criteria in clause 63.3 of NEC3 or the 63.5 in NEC4, it should not add anything on to the Completion Date as planned Completion is not delayed.

However, the Contractor's risk of being later is, in simple terms doubled, as it has two paths of operations which could cause a further planned Completion to go back as opposed to the original one. Consequently, under clause 63.6 (NEC3) / 63.7 (NEC4) the Contractor is entitled to some additional time &/or monies due to the increased risk.