Yes, it is. This is because even thought the work might be identical, the rates don't take into account the delay and sometimes disruption cost.
Alternatively, the game used to be to spot the quantities that would go and load them up.
So the default is DC + Fee, unless the PM and Contractor agree otherwise. Do note that it says 'as a basis' (I think from memory)
Alternatively, the game used to be to spot the quantities that would go and load them up.
So the default is DC + Fee, unless the PM and Contractor agree otherwise. Do note that it says 'as a basis' (I think from memory)