See this link - https://www.linkedin.com/pulse/who-pays-covid-19-contract-risk-allocation-under-nec-contracts-jon/ for a article by yours truly. The long and short of it is that, under NEC3 (the situation is different under NEC4 because of slightly different wording in clause 60.1(19) - that in your circumstances it is probably not a compensation event.
↧