Answered: NEC ECC: Option A with Options X11 incorporated

$
0
0
If it is the Client's declared wish to terminate then you should be using the early warning mechanisms to discuss the issues and the way forward to terminate in a controlled way.

This may well result in some additional instructions - and hence compensation events - to secure the Site, make sure it won't deteriorate etc. rather than the Contractor just dropping tools and walking away on termination.

Post-termination, the mean point of co-operation is to ensure the final account is wrapped up in accordance with the contract provisions.