NEC ECSC: Awarding contract post-covid that was tendered pre-covid and risk,

$
0
0
NEC3 shortform jobs tendered before Covid-19, are now being asked after letters of intent issued for us to allow amending clause 60.1.(12) to read 'Contract Award' in lieu of 'Contractors Offer' thus removing any allowance for change to the programme or any reimbursement from the Authority, is this legal because unless we accept their terms these contracts wont be awarded to us with the next in line being approached in lieu of retendering?

Contracting Authority is the Education Authority with works in Northern Ireland