Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC ECC: Defect correction prior to completion

$
0
0
Sectional Completion and the overall Completion should comply with the definition of Completion in clause 11.2. To achieve Completion it should be free of defects that would prevent the Client or others from using the works. This means it does NOT have to be free of defects in order to achieve Completion. They are still obliged to correct defects after this time and you have remedies under section 4 of the contract if they do not.

Viewing all articles
Browse latest Browse all 3204

Trending Articles