The NEC4C Contract says that the PM issues it 4 weeks after the Supervisor issues the Defects Certificate. It doesn't say if the Contractor is required to submit an application but if there is no application I am not sure how the PM can assess. I would submit your application on the day that the Defects Certificate is issued or shortly thereafter.
↧
Answered: NEC4 Option C - when should the contractor submit the final account- is there a timeline?
↧