Answered: NEC ECC: Should a reference to compliance with CDM Regulations be inserted in the Scope, as a Z clause or both

$
0
0
Lawyers seem to prefer the option Z clauses, but they would wouldn't they!

I see no reason why it can't be in the Scope though and, if being the Principle Consultant is part of their professional services, then putting it in the Scope fits with the contractual definition of what the Scope is!

Further, if it needs modifying in some way, then it can be done by an instruction rather than a Supplementary Agreement if it is the option Z clauses.