Answered: Are you entitled to prelim costs on additional time if you complete early.

$
0
0
You have not specified which contract you are working under to answer this. The fact you are using EOT probably means this is not an NEC contract as it doesn't use that language. It would also depend which NEC contract option you are working under. If it was an NEC ECC option A contract and a compensation event has been agreed including costs for 20 weeks delay which was believed to be a reasonable forecast, then yes they would be paid that agreed cost whether it took then 18 weeks or 22 weeks.