Under clause 62.3, if the Contractor does not provide a quotation then the Employer assesses and notifies the Contractor of his assessment.
The whole CE process is less rigorous in the short contract compared to the ECC, and less recourse if for example the Employer does not respond within the timescale with their assessment.