NEC3 TSC: what's the best way to deal with work carried out by the Contractor under a Task Order that wasn't instructed in the Task Order?

$
0
0
Had a Contractor carry out work under a Task Order that wasn't instructed but they've attempted to claim for it.

Is the best thing to do to notify these items as Defects and be explicit that these events are not compensation events?