Good question but no the second batch of five is NOT dependent upon one of the first three being achieved. The first three are "costs that the Project Manager decides", and the latter five are "costs of ". It would not make any sense if correcting a Defect after Completion was not disallowed if it did not meet the criteria of the first three bullets as most would not.
↧