Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC3 ECC: Delay to planned Completion

$
0
0
If the Contractor is over running by one month with planned Completion one month beyond the Completion Date and there is a compensation event that moves planned Completion by one day, then Completion Date moves by one day (not one month and a day). This is in accordance with clause 63.3 – which emphasises everything is measured against the planned Completion on the last Accepted Programme. If this were not the case the Employer would be reluctant to ever issue compensation events when the Contractor is already in delay if that meant they would no longer be liable for delay damages.

Viewing all articles
Browse latest Browse all 3204

Trending Articles