Answered: NEC3 ECC: Option A, Defined Cost from SSCC or Subcontractor Quote for Compensation Event pricing?

The default position is that compensation events are assessed using Defined Cost - which will be by building up from the (Shorter) Schedule of Cost Components. The fact you have or haven't been using "rates" previously seems to have been by agreement. Unless those rates are tied into the contract and intended to replace elements of the SSCC then they have no standing going forward. If Parties agree, rates or lump sums may be used, but this is on a case by case basis and no contractual precedent will have been set here no matter what has gone on before. I therefore agree with your last sentence.