If the main contract is Option C or D you will need to refer to the subcontract order to see what Fee the subcontractor is entitled to (Subcontract Data Part 2).
If Option A or B then the Fee is not added.
This will enable you to calculate the Defined Cost ie the amount due to the subcontractor, cost + his Fee (where applicable). Only the Subcontracted Fee should be applied to this Defined Cost.