If you have a programme with an activity on the critical path with a duration of 15 days and you have 5 days of TRA included in this (10 + 5) how is this progressed?
If I complete within the 10 days and reschedule the programme does my Planned Completion then just pull in 5 days prior the Contract Completion date and creates float for either contractor or client to then use?
If I complete within the 10 days and reschedule the programme does my Planned Completion then just pull in 5 days prior the Contract Completion date and creates float for either contractor or client to then use?