NEC3 ECC: delay assessment with no accepted programme

$
0
0
The Contractor has submitted a quotation for a CE and included a current accepted programme to show the delay caused, the concern is, is that at the time of the event there was no accepted programme (CL 31), therefore the PM will have to make the assessment.
My question is which programme to use, there had been a number of CL31 programmes issued but rejected for the correct reasons, so should the PM use the accepted programme closest to the CE, which in this case would be 1 month ahead of when the CE was issued, adjust (reduce) the percentage completion against activities to the point at which the CE was issued and then adjust the CE affected activates to show the delay on the date of the planned completion or use a programme that coincides with the time of the CE whether it was rejected or not.
Ant guidance would be appreciated.

Viewing all articles
Browse latest Browse all 3204

Trending Articles