The PM has requested a quotation for works under clause 61.2, a quotation was submitted which was then instructed via a PMI as 'cost to be agreed'. Am I correct that the PM should have either requested a revised quotation or made his own assessment in line with 62.3.
If we have not been instructed in accordance with 61.1 could we assume the costs are agreed?
If we have not been instructed in accordance with 61.1 could we assume the costs are agreed?