Thanks for taking time to reply to me it's greatly appreciated, you are correct the drawings are part of the works information. I've told out client that I wish to price each CE as an individual item under clause 60.4 as they have increased more than 0.5% for an example we have a bill rate for gully's with known connections within the new drawings we have additional gully's with unknown connections I have priced these up using CDP2 some are retrospective using actual time and resources and some have yet to be completed and have been predicted. All of the changes are going on to the updated programme and being forwarded to the client.
The problem I now have is our client is saying he can value the additional items under 63.13 using Bill Rates can he do this.