Answered: NEC3 ECS - Delay Damages - recovering Contractors costs from Subcontractor

$
0
0
Yes. If your Subcontractor is later than their Completion Date then you can only charge them £795/day as per their contract. If your Employer is charging you £795/day for being late, then any other costs that you are incurring would be your problem - there is no where else in the Subcontract that allows you to recover additional cost that you the Contractor are incurring for being late.