Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

NEC3 ECC: CEs after Completion Date (Access restrictions to site)

$
0
0
Works have continued well past the Completion Date due to Contractor delay (there is no dispute on this).  During the works after the Completion Date the Employer has had occasion when access can not be allowed to the site on temporary basis.  Normally this would constitute a CE under 60.1(2), but as the works should have finished before the access restrictions occurred is it still a CE, and if so how should it be valued?

Viewing all articles
Browse latest Browse all 3204

Trending Articles