Under the Engineering and Construction Subcontract the Contractor may give an instruction changing the Subcontract Works Information to remove/reduce the scope of work. This is a CE 60.1(1); quotations are submitted, assessed and implemented. So far so good. Everyone's happy.
The Contractor then decides he is going to give that work to AN Other to complete. In general terms this would be a breach of subcontract by the Contractor and the Subcontractor would be entitled to damages.
A breach of subcontract is a CE under 60.1(18), and as a CE the rules under 63.1 have to be followed - how would the Subcontractor be able to recover damages (loss of profit etc) following these rules?
The Contractor then decides he is going to give that work to AN Other to complete. In general terms this would be a breach of subcontract by the Contractor and the Subcontractor would be entitled to damages.
A breach of subcontract is a CE under 60.1(18), and as a CE the rules under 63.1 have to be followed - how would the Subcontractor be able to recover damages (loss of profit etc) following these rules?