Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

NEC3 ECC: Change in quantity under option D

$
0
0
Say the Original BOQ for Pile Test  500 ea @ £100, then qty later revised /reduce (due to redesign by owner) to 300 ea, with 100 ea already done @ £50 (actual cost each) and 200  not yet done.  What is the correct approach to reduce the Target Price using Option D?

The guidance note says that you consider the actual define cost for works already done plus forecast the defined cost.  Is the result of this becomes the new price? or do u have to deduct the result from the original target cost for the item, to get the revised target cost?

Viewing all articles
Browse latest Browse all 3204

Trending Articles