Answered: NEC3 ECC: Option A itemised Activity Schedule - can I raise an EW if I feel client is asking for contractor to complete more work than we assessed was required.

$
0
0
If the area marked out is greater then that shown on the drawings then there has been a changed in the Works Information and it is a CE. Whether the original area billed was equal to the area shown on the drawings is academic (this was the contractor's risk unless the BOQ is stated as Works Information)