Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC3 ECC: Uplift in claimed principal contractor sub-contractor costs as a result of actual delay - Who pays?

$
0
0
Depends if the reason for the reason for "actual delay" is a compensation event or not. If it is a compensation event then potentially yes (as long as they can prove it is an element of Defined Cost), otherwise if not a compensation event then there is no way for the Contractor to recover this cost.

Answer also depends on which ECC option you are working under. If this is option C, then any overspend by the Contractor that is not dis-allowable is shared under the pain/gain mechanism.

If ever a Contractor says "can I claim for this thing", my answer is always "show me where in clause 60.1 that thing is a compensation event" then yes you can clam for it.

Viewing all articles
Browse latest Browse all 3204

Trending Articles