Reading the contract as :
- the Contractor has tendered 'prices' (in italics) for "work which the Contractor will do himself" (in the Contract Data Part 2); and
- a Disallowed Cost "is a payment to a Subcontractor for - work which the Contract Data stated the Contractor will do himself"
then it is pretty clear that it is a Disallowed Cost.
The question becomes 'is the Contractor paid at all for this work now ?'
- the Contractor has tendered 'prices' (in italics) for "work which the Contractor will do himself" (in the Contract Data Part 2); and
- a Disallowed Cost "is a payment to a Subcontractor for - work which the Contract Data stated the Contractor will do himself"
then it is pretty clear that it is a Disallowed Cost.
The question becomes 'is the Contractor paid at all for this work now ?'