Under any of the NEC3 contracts once a compensation event is implemented (i.e. PM in writing has confirmed the cost and/or movement in Completion Date) then it is not revisited if it is later found out to be wrong. If you do it one day quicker or take three days longer the CE assessment stands.
↧