What is clause 60.1(8) specifically intended to pick up that clause 60.1(1) would already cover? If the Project Manager changes a decision that changes the Works Information then this would be covered by 60.1(1). So what examples are there of the kind of thing that would be picked up by 60.1(8) such that it was necessary to include within the contract?
↧