The Contractor should revise their activity schedule and spread that cost elsewhere within the other items on the activity schedule. It is a lump sum fixed price. If an item is not done it does not mean the Employer does not pay it - likewise if a Contractor does double what they thought of an item on the activity schedule they cant claim extra as a change in activity schedule alone is not a CE.
↧