Depends how the PMI has been instructed. If this is under 61.1, the Contractor is obliged to proceed in meantime in lieu of quotation being agreed. It would then be a new instruction to stop these works and any costs incurred would be recoverable.
If however the quotation was instructed under 61.2 for a proposed element of works then currently no if this does not go ahead there is no way of recovering that cost.
However, it would seem as though NEC4 has addressed this and there will be means of recovery of the cost of a quote for a 61.2 that does not then go ahead.
If however the quotation was instructed under 61.2 for a proposed element of works then currently no if this does not go ahead there is no way of recovering that cost.
However, it would seem as though NEC4 has addressed this and there will be means of recovery of the cost of a quote for a 61.2 that does not then go ahead.