NEC3 ECC: Time cost build up under Option C

$
0
0
We are a Contractor based from our own office, which for the duration of the contract is deemed part of the Working Area. I am currently preparing a CE quotation that includes a 5 week extension to the programme.

I am including all the management staff in the time element of the claim and applying the Working Area overhead and fee to same.

My question is, could I apply a proportion of the actual head office overhead to this CE as I believe it exceeds the overhead amount for people in the contract?