NEC ECC: Option A Subcontractor fee percentage

$
0
0
NEC Option A - Activity schedule.

We have received a quote which the subcontractor has applied fees which are higher than the tendered fees submitted by the main contractor. Ie they have applied a 20% fee to their design element.

Am I correct in applying the main contractors fee % to the relative categories of the subcontractor cost breakdowns? Ie I should apply the tendered fee percentage of 0% to that element.