Answered: NEC ECC: Assessment of change

$
0
0
Put simply, it sounds as if the Project Manager is assessing it incorrectly as the circumstances as I have changed in two respects :
a. the door schedule has changed;
b. the programme has changed which may well have time and cost impacts.

It is implied that the PM can change a decision which has previously been communicated to the Contractor and this is a compensation event