NEC ECC: Compensation event due to changes in works information during tendering stage.

$
0
0
The PM is claiming that during a compulsory site briefing it was pointed to the Contractor that the building to be renovated is a live building hence the Contractor should have incorporated pricing for phase movement of people during construction or for hiring mobile classrooms. However, the original works information drafted in the tender document makes no mention of the methodology that the Contractor should follow during construction since it's a live building. The Contractor is therefore raising a Compensation event since now we need to hire mobile classrooms in order to work in phases, the PM is claiming that the Contractor should have made necessary arrangements to provide the works and to pricing since this was pointed out during site briefing, however still the Employer didn't mention a specific methodology of working or even if the Contractor is to design the methodology under contract data part 2.

Viewing all articles
Browse latest Browse all 3204

Trending Articles