While the actual amount will depend on the contract reason, every reason includes amount A1 as articulated in clause 93.1.
The third main bullet is for "other Defined Costs reasonably incurred in expectation of completing the works".
Without knowing the specifics of their employment contracts, I would have thought that the cost of employing people in expectation of completing the works is a Defined Cost as, to avoid this cost, you would have had to terminated their employment contracts early before you got the termination instruction.
The third main bullet is for "other Defined Costs reasonably incurred in expectation of completing the works".
Without knowing the specifics of their employment contracts, I would have thought that the cost of employing people in expectation of completing the works is a Defined Cost as, to avoid this cost, you would have had to terminated their employment contracts early before you got the termination instruction.