A Contractor under option C has included TRA as a "cost of his risk for not being in a position to complete activities" impacted by a CE within his quotation.
I believe that he is entitled to the time not the "perceived value" of the time i.e. he has lost 4 days of TRA which he has grouped for a sequence of activities with no itemized TRA. is this allowable under option C assessment of compensation events?
I believe that he is entitled to the time not the "perceived value" of the time i.e. he has lost 4 days of TRA which he has grouped for a sequence of activities with no itemized TRA. is this allowable under option C assessment of compensation events?