Whilst the PM agreed that a delay occurred the subject NCE was rejected on the basis that the Contractor was not ready to start the works due to their fault and as such no entitlement existed, however this delay would have impacted the existing agreed programme, was the PM correct to reject this NCE on this basis due to their interpretation of no impact on defined cost ?
↧