Let's step back.
1. You say the "Client/Contractor needs to supply us with water and dust proof Storage facility". Can you confirm this is stated in the subcontract Works Information along with dates etc. when it would be supplied to you ?
2. You say you "have raised a CE advising the contractor that he has not supplied something he should have supplied" yet "The PM has rejected the EWN". You have 'advised' the Contractor (not notified), yet it the ?Employer's? PM who has not accepted it. And there is no facility in the ECC for the PM to "reject" EWs. Can you clarify ? E.g. is the Employer's PM saying why the hell has a subcontractor 'advised' me of an early warning rather than the Contractor ?
Please clarify and then we can look at a way forward.
1. You say the "Client/Contractor needs to supply us with water and dust proof Storage facility". Can you confirm this is stated in the subcontract Works Information along with dates etc. when it would be supplied to you ?
2. You say you "have raised a CE advising the contractor that he has not supplied something he should have supplied" yet "The PM has rejected the EWN". You have 'advised' the Contractor (not notified), yet it the ?Employer's? PM who has not accepted it. And there is no facility in the ECC for the PM to "reject" EWs. Can you clarify ? E.g. is the Employer's PM saying why the hell has a subcontractor 'advised' me of an early warning rather than the Contractor ?
Please clarify and then we can look at a way forward.