Question 1 - Delay Damages will be a complete remedy for time related costs. Therefore, no standing time cannot be claimed above the delay damages limit.
Question 2 - Under X18.4 this is total liability, that is both direct and indirect. There are two different percentages with different regimes, you seem to be mixing them. I cannot see standing time as consequential, it is really direct.
Question 3 - If you have X7 for delay damages then that is one of the matters to be taken into account in the monthly payment (ie amounts the contractor owes to the employer). If you do not have a delay damages provision then you would make the deduction in the same way but stated as a consequence of breach of contract so damages.
Question 4 - X18.4 is for total liability howsoever arising except for the excluded matters. So, examples could be defects, damage to adjoining property, environmental prosecution and so on. X7 is excluded so does not fall under the total cap. So, if the total cap is £1m and delay damages are capped at £1m and you suffer £800k of damage to adjoining land and the delay damages calculation amount to £1.5m then you have the whole of the £800k and £1m of delay damages total recovery £1.8m
Question 2 - Under X18.4 this is total liability, that is both direct and indirect. There are two different percentages with different regimes, you seem to be mixing them. I cannot see standing time as consequential, it is really direct.
Question 3 - If you have X7 for delay damages then that is one of the matters to be taken into account in the monthly payment (ie amounts the contractor owes to the employer). If you do not have a delay damages provision then you would make the deduction in the same way but stated as a consequence of breach of contract so damages.
Question 4 - X18.4 is for total liability howsoever arising except for the excluded matters. So, examples could be defects, damage to adjoining property, environmental prosecution and so on. X7 is excluded so does not fall under the total cap. So, if the total cap is £1m and delay damages are capped at £1m and you suffer £800k of damage to adjoining land and the delay damages calculation amount to £1.5m then you have the whole of the £800k and £1m of delay damages total recovery £1.8m