At the beginning of the contract the Employer's Project Manager named in the contract data delegated his duties to another person until the completion date of the project.
Is this a change in Project Managers?
Can both PMs give instructions? (If the original PM gives an instruction is this then a valid instruction?)
Is this a change in Project Managers?